EXPERIENCE IN TANZANIA
We were also awarded an extremely difficult and challenging TZ drilling and loading project offshore Tanzania. This required our rigs to work on reefs and islands that were normally submersed during high tide which meant that the logistics had to be precise otherwise safety would be compromised and too much time would be lost due the fast moving tides.
Tanzania Project History
| Year | Project | Size (km) | Start | Finish |
|---|---|---|---|---|
| 2011 | Ruvu Phase I | 590 | 15/07/2011 | 25/11/2011 |
| 2012 | Ruvu Phase II | 170 | 14/01/2012 | 03/03/2011 |
| 2012 | Nyuni TZ | 480 | 08/05/2012 | 28/06/2012 |
| 2012 | Ruvi Phase III | 190 | 20/07/2012 | 10/08/2012 |
| 2012 | Ruvi Phase IV | 550 | 24/02/2013 | On – Going |
A total of 1,500km’s has been acquired to date in and around this area working exclusively during the two yearly dry seasons of Tanzania.The first project commenced in 2011 and we have been directly awarded 3 consecutive extensions from the same client since we began operations in Tanzania.